Interconnection queues: MW and wait times

US interconnection queues held 2,061 GW of proposed generation and storage at year-end 2025. Completed projects took a median 60.8 months from request to operation in 2025. Berkeley Lab’s sample excludes large loads; the tracker reports those separately, alongside resource MW, historical outcomes and dated reform milestones.

242 sourced readings · Download readings · 49 operator and provider listings

49 listings 52 directory sources, each dated Checked

How much is queued, and how long did projects take?

Full tracker

Storage includes estimated hybrid MW in LBNL’s regional summaries. Nuclear uses reported project-level MW. Total includes other resources. Waits cover completed projects with measured dates, not today’s applicants. Inspect each reading and its calculation.

Queue size and measured waits

Completion and withdrawal rates

Active generation and storage

GW · 31 December 2025 ERCOT: 408 GW · 09. Active Cap. Region+Type: D271, D272, D273, D274, D275, D276, D277; GW × 1,000 ERCOT 408 MISO: 382.2 GW · 09. Active Cap. Region+Type: D439, D440, D441, D442, D443, D444, D445; GW × 1,000 MISO 382.2 CAISO: 191.3 GW · 09. Active Cap. Region+Type: D187, D188, D189, D190, D191, D192, D193; GW × 1,000 CAISO 191.3 SPP: 171.2 GW · 09. Active Cap. Region+Type: D775, D776, D777, D778, D779, D780, D781; GW × 1,000 SPP 171.2 PJM: 144.3 GW · 09. Active Cap. Region+Type: D607, D608, D609, D610, D611, D612, D613; GW × 1,000 PJM 144.3 NYISO: 29.2 GW · 09. Active Cap. Region+Type: D523, D524, D525, D526, D527, D528, D529; GW × 1,000 NYISO 29.2 ISO-NE: 14.8 GW · 09. Active Cap. Region+Type: D355, D356, D357, D358, D359, D360, D361; GW × 1,000 ISO-NE 14.8
One LBNL snapshot and population. Click a bar for its source and calculation. MW in requests are proposed capacity.

Request to commercial operation

median months · year reaching COD 020406080 2015: 37.8 months · n=164 2015 37.8 2016: 44 months · n=180 2017: 39.9 months · n=138 2017 2018: 41.9 months · n=152 2019: 46.5 months · n=153 2019 2020: 46.1 months · n=227 2021: 50 months · n=200 2021 2022: 55.2 months · n=176 2023: 55.7 months · n=265 2023 2024: 62.7 months · n=335 2025: 60.8 months · n=294 2025 60.8 LBNL sample · completed projects
These medians include development after study completion. They are historical elapsed times, not a promised wait for a new project.

Queue operators, data, software and study firms

49 sourced listings
Alberta Electric System Operator (AESO)Public queue operator—Project list, interactive map and Power BI dashboardsGeneration, energy storage and load facilities——2026-11-11
Bonneville Power Administration (BPA)Public queue operator—Request queue and queue mapLarge and small generation; line and load connections—Federal Columbia River Transmission System2026-11-11
Burns & McDonnellStudy and advisory———Power flow, transient stability and bus flow analysis for cluster studies—2026-11-11
California ISO (CAISO)Public queue operator—————2026-11-11
Clean Power ResearchSoftwarePowerClerkNo-code SaaSLarge generators and large loads——2026-11-11
Danovo Energy SolutionsStudy and advisory—Engineering, analytics and advisory services———2026-11-11
DNVStudy and advisory———Thermal/voltage, dynamic stability, short circuit/protection and electromagnetic transient impacts—2026-11-11
Dominion EnergyPublic queue operatorVirginia Queue Status Report————2026-11-11
Duke EnergyPublic queue operator—Duke Energy Progress generation study results downloadable from OASIS Generator Interconnection Information folderDistributed renewable generation and storageCluster studies described for distributed generation in June 2024—2026-11-11
Electric Power Engineers (EPE)Study and advisoryGrid Analysis & Interconnection——Transmission planning and operations servicesERCOT and Eastern Interconnect, including SPP, MISO, PJM, ISO-NE, NYISO and SERC (2025 service-team description)2026-11-11
EnerzinxStudy and advisory——Renewables, data centers and utility-scale energy——2026-11-11
EnverusQueue data and analyticsInterconnect———All 7 US ISOs2026-11-11
ERCOTPublic queue operatorGenerator Interconnection Status (GIS) report—Planned generation in ERCOT region——2026-11-11
Grid StatusQueue data and analytics—Open-source Python library and hosted REST API——Integrations for CAISO, ERCOT, PJM, MISO, SPP, NYISO, ISO-NE, IESO and AESO; dataset coverage varies2026-11-11
GridCAREStudy and advisoryGridCARE Energize————2026-11-11
gridmoSoftware—Software platform for grid connection studies———2026-11-11
GridTrackerQueue data and analytics—Browser interface and MCP connector——US interconnection queues2026-11-11
GridUnitySoftwareGridInterConnect for TransmissionCloud-based SaaS———2026-11-11
ICFStudy and advisory——Generation and load connections——2026-11-11
Independent Electricity System Operator (IESO)Public queue operator——Transmission, load, generation and ancillary services——2026-11-11
ISO New EnglandPublic queue operator—Public queue with PDF and XLSX export guidanceNew/uprated generation, elective transmission upgrades and transmission service——2026-11-11
KevalaSoftwareIntegrated Grid Planning (IGP)—Load and distributed generation scenarios——2026-11-11
LandGateQueue data and analyticsOfftake ReportReports and MCP server———2026-11-11
Lawrence Berkeley National LaboratoryQueue data and analyticsQueued Up: 2026 Edition———7 ISOs/RTOs and 50 non-ISO utilities2026-11-11
MISOPublic queue operatorGenerator interconnection process and GIA Portal————2026-11-11
National Energy System Operator (NESO)Public queue operatorTransmission Entry Capacity (TEC) RegisterCSV and CKAN Data API———2026-11-11
New York Independent System Operator (NYISO)Public queue operator——Large-load interconnection requests are reported in the Gold Book——2026-11-11
Nira EnergyQueue data and analytics——Generation and load developmentERIS and NRIS study replication—2026-11-11
PacesStudy and advisoryDevelopment-as-a-ServiceServices tracked within Paces platform———2026-11-11
Pacific Gas and Electric (PG&E)Public queue operatorPublic wholesale distribution queueXLSX download—Cluster Study Process evaluates requests collectively—2026-11-11
PacifiCorpPublic queue operator—————2026-11-11
PJM InterconnectionPublic queue operatorCycle Service Request StatusFull and filtered exports in XLS and XML—SIS reports include facility and affected-system studies—2026-11-11
PowerGEMSoftwareTARABatch, multi-core and cloud licensing—N-1 and N-1-1 contingency analysis—2026-11-11
PowerWorld CorporationSoftwarePowerWorld Simulator——Generator interconnection studies with steady-state security analysis—2026-11-11
PSC ConsultingStudy and advisory———Feasibility and interconnection studies—2026-11-11
Pterra ConsultingStudy and advisorydqBOT IBR model-validation automation—DER evaluation and load interconnection engineeringGeneration interconnection, feasibility and impact studies—2026-11-11
PVcaseSoftwarePVcase Prospect Capacity—Includes BESS charging studiesN-1 injection studies by busUS project sites only2026-11-11
RLC EngineeringStudy and advisory——Solar, wind and battery resources on transmission and distribution systemsDER cluster studies—2026-11-11
S&P Global Market IntelligenceQueue data and analytics2026 US Interconnection Queues Analysis report———2023 analysis covers all 7 US ISOs and 14 major non-ISO utilities; historical report scope2026-11-11
SiemensSoftwareGridscale X PSS E————2026-11-11
Smarter Grid SolutionsSoftwareFlexible Grid Interconnections powered by Strata GridControls do not depend on a network modelDistributed generation, energy storage and large loads——2026-11-11
Southern California Edison (SCE)Public queue operatorPublic interconnection queue and redacted study reports—WDAT and Rule 21 non-export requests accepted in tool——2026-11-11
Southern Company TransmissionPublic queue operatorActive OATT requests in transitional cluster study listing————2026-11-11
Southwest Power Pool (SPP)Public queue operator—Public listing and CSV download———2026-11-11
TNEIStudy and advisory————US data-center interconnection services2026-11-11
Wood MackenzieQueue data and analyticsLens Power & Renewables queue data———US interconnection queues2026-11-11
WSPStudy and advisory———TRV and TOV dynamic stability studiesUnited States study reference portfolio2026-11-11
Xcel EnergyPublic queue operatorDistributed Energy Resources interconnection queue———Minnesota distributed generation interconnection2026-11-11
Yes EnergyQueue data and analyticsInfrastructure Insights———North America2026-11-11

Browse by what you need

  • Public queues 18

    Find ISO, RTO and utility interconnection queues for PJM, MISO, SPP, ERCOT, CAISO, NYISO and ISO-NE, with published fields, formats, timing and source links.

  • Queue data 9

    Compare interconnection queue data: LBNL Queued Up, GridTracker, Enverus, Grid Status, Wood Mackenzie and S&P, with coverage, refresh and sources.

  • Software 9

    Compare interconnection software for queue workflows and power-flow studies, including GridUnity, PowerClerk, PSS E, PowerWorld and TARA, with dated sources.

  • Studies and advisory 13

    Interconnection study and advisory firms compared: study types, request types, application support and published track record, with first-party source links.

  • Large load 12

    Find operators, software and study firms that track and model large-load and data center interconnection requests, with service scope, sources and dates.

How to read the table

Full methodology

Each row is a queue, a queue dataset, a tool or a firm, read from its own page. The small number beside a value opens that source with the date we read it. A blank cell means the source states nothing on that point.

The queue tracker records dated measurements. Each row names its population and unit, with a report or workbook locator. The operator and provider directory below it describes services, formats and fees.

Dates in a queue are requests, not promises. A proposed in-service date shows what a developer asked for, so waits appear here only where a named report measures them. Featured placement is paid and labelled; every row sorts on its own data.

Questions developers ask

Who runs interconnection queues?

Each grid operator runs its own. In the US that is seven ISOs and RTOs (PJM, MISO, SPP, ERCOT, CAISO, NYISO and ISO New England), plus transmission-owning utilities such as PacifiCorp, Southern Company, PG&E, SCE, Xcel, Dominion and Duke outside them. Canada has IESO and AESO, Great Britain has NESO, and BPA runs the federal Columbia River system. All 18 are in the table with what each publishes: SPP offers a CSV download, PJM exports XLS and XML, NESO updates its register every Tuesday and Friday.

Sources: PJM cycle status, SPP active requests, NESO TEC Register, LBNL Queued Up

How long is the wait in an interconnection queue?

Projects that reached commercial operation in 2025 took a median 60.8 months from interconnection request, just over five years, across 294 projects with measured dates in Berkeley Lab’s Queued Up 2026 data. The 2015 median was 37.8 months. The wait depends on the grid: 109.6 months in CAISO (14 projects), 82.6 months in PJM (46), 56.1 months in SPP (138) and 48 months in ERCOT (74). MISO’s temporary ERAS track aims to issue an agreement in three months. A proposed in-service date in a queue is the developer’s request; these medians are measured.

Sources: LBNL Queued Up, MISO generator interconnection, Queued Up 2026 workbook (sheets 37–38)

What does it cost to join a queue?

MISO charges a flat $7,600 application fee and an M2 milestone of $8,000 per MW studied, in cash or an irrevocable letter of credit; the 2026 DPP cycle closes on 15 January 2027. Xcel Energy charges $300 for a Pre-Application Report in Minnesota. PG&E opened its QC16 cluster window from 11 to 25 September 2026. Fees and security are set per operator and per request size, so read the tariff of the queue you are joining.

Sources: MISO generator interconnection, Xcel Energy hosting capacity, PG&E wholesale generation

Where can I download queue data?

Straight from the operators: SPP and NESO offer CSV, PJM XLS and XML, ISO-NE PDF and XLSX, PG&E XLSX. For one dataset across operators use Berkeley Lab’s Queued Up (CC BY 4.0, 7 ISOs and RTOs plus 50 non-ISO utilities, data through the end of 2025), GridTracker’s daily snapshots with history since April 2024, or the open-source Grid Status Python library (BSD-3-Clause). Enverus tracks all 7 US ISOs daily.

Sources: LBNL Queued Up, GridTracker, Grid Status on GitHub, Enverus (Pearl Street) Interconnect

Where are data center (large-load) requests tracked?

Operators now publish their own large-load counts. ERCOT conditionally placed 66.4 GW of large load (204 projects) in its Batch Zero study on 3 September 2026, per its September Batch Zero Update. AEP Ohio holds 17,861 MW of contracted data-center load, per its 13 February 2026 release. NYISO reports large-load requests in its Gold Book, and IESO and AESO list load applications beside generation. On the services side, TNEI manages data-center requests from 10 MW to 500 MW and above, and GridCARE says it has qualified 5 GW of capacity across the US. The large-load hub lists all 12 entries.

Sources: ERCOT Batch Zero Update, Sept 2026, AEP Ohio, 13 Feb 2026, NYISO 2024 Gold Book, IESO application status, TNEI data-center services, GridCARE